Scheduling

Central Park Row Homes

Project Scheduling


Please note all dates are based on weather and delivery of materials to complete the project scope of work.

COVID-19 has created material production and delivery delays across the building industry.

Please note that buildings/units will be posted with information fliers and work dates for direct resident communication for scheduling.

Materials with longer lead times are currently: windows, specialty metal, window glazing bead and some paint/stain colors with a deep base and shutters. Repairs with these materials may be scheduled after the preliminary repair schedule due to material availability.


Preliminary Repair Schedules - by Buidling


Flat Roof Style Buildings

Building 14 (2930, 2932, 2934, 2936, 2938, 2940 Uinta St)

Re-Roof Schedule - June 6th - June 18th 2022 - Completed

Repairs & Repaint Schedule - June 1st to June 13th 2022 - Repairs & full repaint completed - Custom metal - November - December 2022

Building 15 (2933, 2935, 2937, 2939, 2941, 2943 Central Park Blvd)

Re-Roof Schedule - June 6th - June 18th 2022 - Completed

Repairs & Repaint Schedule - June 1st to June 13th 2022 - Repairs & full repaint completed - Custom metal - November - December 2022

Building 16 (2936, 2938, 2940, 2942, 2944, 2946 Central Park Blvd)

Re-Roof Schedule - June 13th - June 18th 2022 - Completed

Repairs & Repaint Schedule - June 6th to July 2nd 2022 - Repairs and full repaint completed - Custom metal - November - December 2022

Building 1 (8703, 8705, 8707, 8709, 8713, 8715, 8717, 8719 E 29th Pl)

Re-Roof Schedule - June 27th - July 1st 2022 - Completed - Complete

Repairs & Repaint Schedule - June 27th - July 20th 2022 - Repairs and full repaint completed - Custom metal - November - December 2022

Building 2 (8723, 8725, 8727, 8729, 8733, 8735, 8737, 8739 E 29th Pl).

Re-Roof Schedule - July 5th - July 18th 2022 - Completed

Repairs & Repaint Schedule - June 27th - July 20th 2022 - Repairs and full repaint completed - Shutters & custom metal - November - December 2022

Building 3 (2953, 2955, 2957, 2959, 2961, 2963, 5965, 2967 Xenia St)

Re-Roof Schedule - July 5th - July 18th 2022 - Completed

Repairs & Repaint Schedule - June 27th - July 20th 2022 - Repairs and full repaint completed - Shutters & custom metal - November - December 2022

Building 4 (2954, 2956, 2958, 2960, 2962, 2964, 2966, 2968 Xenia St).

Re-Roof Schedule - July 20th - August 1st 2022 - Complete

Repairs & Repaint Schedule - June 27th - July 2022 - Repairs and full repaint completed - Shutters & custom metal - November - January 2023

Building 5 (8903, 8905, 8907, 8909, 8913, 8915, 8917, 8919 E 29th Pl).

Re-Roof Schedule - July 20th - August 1st 2022 - Roofing Completed - Complete

Repairs & Repaint Schedule - July 27th - August 9th 2022 - Repairs and full repaint completed - Custom metal - November - January 2023

Building 6 (8929, 8925, 8927, 8929, 8933, 8935, 8937, 8939 E 29th Pl).

Re-Roof Schedule - August 8th - August 19th 2022 - Complete

Repairs & Repaint Schedule - August 15th - August 26th 2022 - Repairs and full repaint completed - Custom metal - November - January 2023

Building 25 (8705, 8707, 8709, 8715, 8719, 8725, 8733, 8735, 8745 E 25th Ave).

Re-Roof Schedule - August 15th - September 12th 2022 - Complete

Repairs & Repaint Schedule - August 15th - Sept 27th 2022 - Repairs and full repaint completed - Shutters & custom metal - December- February 2023

Building 26 (8755, 8757, 8759, 8765, 8767, 8775, 8783, 8785, 8795 E 25th Ave).

Re-Roof Schedule - August 17th - September 16th 2022 - Complete

Repairs & Repaint Schedule - August 22nd - September 19th 2022 - Repairs and full repaint completed - Shutters & custom metal - December- February 2023

Shingle Roof Style Buildings

Building 11 (8101, 8109, 8111, 8119, 8121, 8129 E 29th Ave).

Roof Repair Schedule - Complete

Repairs & Paint Schedule - Repairs Completed

Building 12 (8131, 8139, 8149, 8151, 8159 E 29th Ave).

Roof Repair Schedule - Completed

Repairs & Paint Schedule - Repairs Completed - Garage door replacement - December 2022

Building 13 (8161, 8169, 8171, 8179, 8181, 8189 E 29th Ave).

Re-Roof Schedule - Completed

Repairs & Paint Schedule - Repairs Completed

Building 17 (8201, 8221, 8251, 8261, 8271, 8291 E 29th Ave).

Re-Roof Schedule - Completed

Repairs & Paint Schedule - Repairs Completed - Window Replacements - November - December 2022

Building 18 (8310, 8311, 8321, 8331, 8341 E 29th Ave).

Re-Roof Schedule - Completed

Repairs & Paint Schedule - Repairs Completed - Window Replacements - November - December 2022

Building 19 (8351, 8361, 8371, 8381, 8391, 8393 E 29th Ave).

Re-Roof Schedule - Completed

Repairs & Paint Schedule - Repairs Completed - Garage Door & Window Replacements - November - December 2022

Building 20 (8401, 8411, 8421, 8431, 8441, 8451, 8461 E 29th Ave).

Re-Roof Schedule - Completed

Repairs & Paint Schedule - Repairs Completed - Window Replacements - December- January 2023

Building 21 (8471, 8481, 8491, 8501, 8511 E 29th Ave).

Re-Roof Schedule - Completed

Repairs & Paint Schedule - Repairs Completed - Window Replacements - December - January 2023

Building 22 (8521 8531, 8541, 8551, 8561, 8571, 8581 E 29th Ave).

Re-Roof Schedule - Completed

Repairs & Paint Schedule - Repairs Completed - Window Replacements - December - January 2023

Building 7 (2203, 2213, 2221, 2223, 2225 Valentia St).

Re-Roof Schedule - Completed

Repairs & Paint Schedule - Garage Doors Outstanding

Building 8 (2231, 2233, 2235, 2241, 2243, 2245 Valentia St).

Re-Roof Schedule - Completed

Repairs & Paint Schedule - Garage Doors Outstanding

Building 9 (2251, 2253, 2255, 2261, 2263, 2265 Valentia St).

Re-Roof Schedule - Completed

Repairs & Paint Schedule - Garage Doors Outstanding

Building 10 (2281, 2283, 2285, 2291, 2293, 2295 Valentia St).

Re-Roof Schedule - Completed

Repairs & Paint Schedule - Garage Doors Outstanding

Building 23 (2445, 2447, 2449 Xanthia St).

Re-Roof Schedule - Completed

Repairs & Paint Schedule - December 2022

Building 24 (2493, 2495, 2497, 2505, 2507, 2509 Xanthia St).

Re-Roof Schedule - Completed

Repairs & Paint Schedule - December 2022

The remaining shingle slope buildings are currently being scheduled - please check back for an update soon. Thank you

Concrete Repairs in the Central Park Rowhomes Community

Concrete Repairs HOA Approved 2022 Phase - Complete - Final Detailing & Cleaning In Progress